Relationship: Start to Finish

While there may be (limited) valid scenarios where SF ties are justified, they should be used judiciously and with a clear, well-documented rationale. The key is to strike a balance between accurately representing task dependencies and maintaining a schedule that is clear, transparent, and adaptable to changes. High numbers of SF ties can introduce confusion, complexity, and the risk of schedule delays, which can hinder effective project management.


  • Ambiguity: SF ties can introduce ambiguity and lack of clarity in the schedule. It may be difficult to determine why SF ties are used and what specific purpose they serve in task sequencing.
  • Unconventional Logic: SF ties represent a less common type of task dependency compared to finish-to-start (FS) ties, which are more intuitive and widely understood. The use of SF ties can deviate from conventional project management practices, potentially causing confusion among team members and stakeholders.
  • Misrepresentation of Dependencies: SF ties may not accurately represent the real-world dependencies between tasks. This can lead to inaccuracies and distortions in the schedule, making it challenging to assess the impact of delays or changes.
  • Risk of Schedule Delays: SF ties can introduce unnecessary dependencies, potentially leading to schedule delays. These dependencies can create constraints and limit the flexibility of the schedule, making it less adaptable to changes.
  • Limited Transparency: A schedule with a high number of SF ties may lack transparency and clarity, making it difficult for team members and stakeholders to understand the sequence of work and task relationships.
  • Complexity: SF ties can add complexity to the schedule without clear benefits. This complexity can hinder effective communication, coordination, and management of the project.
  • Difficulty in Critical Path Analysis: SF ties can complicate critical path analysis, which is essential for determining the sequence of tasks that directly impact the project's overall duration. The presence of SF ties may make it challenging to identify the true critical path.
  • Misleading Reporting: Introducing SF ties can result in misleading progress reporting. It may appear that certain tasks are progressing according to schedule, when in fact, they may be delayed.