Delay Table Definitions

Project Delay or “Critical Path Delay” is calculated by identifying activities that were on the schedule’s “Longest Path” at specific points in time, and measuring “delay days” for the period in which the activities are on the longest path.

SmartPM’s Delay Table indicates the following for each schedule update:

mceclip0.png

 

Examples of Delay and Recovery calculations are as follows: